Analisa Biaya Dan Produktivitas Alat Berat Pada Pekerjaan Peningkatan Jalan Blok C Sabak Timur Lambur Ii Muara Sabak

  • Elvira Handayani Universitas Batanghari Jambi
  • Annisaa Dwi Retnani Universitas Batanghari Jambi
  • Rioni Rizki Aldiansyah Universitas Batanghari Jambi
  • Randy Akbar Universitas Batanghari Jambi
Keywords: Cost, heavy equipment, productivity, time.

Abstract

ABSTRAK

Penelitian ini membahas tentang Analisa Biaya dan Produktivitas Alat Berat pada Pekerjaan  peningkatan Jalan Blok C Sabak timur Lambur II Muara Sabak, adapun tujuan dari Analisa Biaya dan Produktivitas Alat Berat ini yaitu untuk Menghitung Analisa Biaya Produktivitas Alat Berat Dump Truck, Motor Grader, Vibrator Roller, dan water tank. Dalam menganlisa data digunakan  metode yang diperoleh dari referensi buku-buku. Metode perhitungan yang digunakan diantaranya melalui buku kapasitas dan Produktivitas Alat-Alat Berat yang diterbitkan oleh Ir.Rochamhadi, 1983. Dari hasil analisa data didapatkan Produktivitas alat berat Dump truck adalah 4,58 m3/jam.Produktivitas alat berat Motor Grader adalah 2367,99 m2/jam. Produktivitas Vibrator Roller adalah 121,50 m3/jam untuk pemadatan timbunan tanah dan untuk pemadatan pekerjaan agregat kelas b adalah 67,50 m3/jam. Produktivitas water tank adalah 11,14 m3/jam. Selisih biaya alat berat harga perkiraan sendiri dan kontraktor adalah sebagai berikut, untuk harga perkiraan sendiri total biaya Rp. 473.200.844 dan kontraktor  total biaya Rp. 506.629.500 didapat selisih biaya alat berat Rp. 33.491.656 dengan persentase 6,61 % terhadap biaya pemakaian alat berat.

Kata Kunci : Biaya, alat berat, produktivitas, waktu.

 

ABSTRACK

 

This study discusses the Analysis of Cost and Productivity of Heavy Equipment in the work of improving the Road Block C, East Sabak, Lambur II, Muara Sabak, while the purpose of the Analysis of Cost and Productivity of Heavy Equipment is to calculate the Productivity Cost Analysis of Heavy Equipment Dump Truck, Motor Grader, Vibrator Roller, and water tanks. In analyzing the data used methods obtained from reference books. The calculation methods used include the book capacity and productivity of heavy equipment published by Ir. Rochamhadi, 1983. From the results of data analysis, the productivity of heavy equipment dump trucks is 4.58 m3/hour. The productivity of the Motor Grader machine is 2367.99 m2/hour. The productivity of the Vibrator Roller is 121.50 m3/hour for compaction of the soil embankment and for compaction of class b aggregate work is 67.50 m3/hour. The productivity of the water tank is 11.14 m3/hour. The difference between the cost of heavy equipment and the contractor's self-estimated price is as follows, for the self-estimated price the total cost is Rp. 473,200,844 and the contractor's total cost is Rp. 506,629,500 obtained the difference in the cost of heavy equipment Rp. 33,491,656 with a percentage of 6.61% of the cost of using heavy equipmen

 

Keywords: Cost, heavy equipment, productivity, time.

References

Hardiyatmo, Hary Christady. (2015). Perencanaan Perkerasan Jalan & Penyelidikan Tanah. Yogyakarta: UGM Press.

Peraturan Pemerintah, 2006, PP No. 34 Tahun (2006) Tentang Jalan, Jakarta.

Rochmanhadi, (1982). Alat-alat Berat dan Penggunaannya, Departemen Pekerjaan Umum, Jakarta.

Rochmanhadi, (1983). Kapasitas dan Produksi Alat-Alat Berat, Departemen Pekerjaan Umum, Jakarta.

Rostiyanti, S.F. (2008). Alat Berat Untuk Proyek Konstruksi - Edisi Kedua. Jakarta: Rineka Cipta.

Undang-Undang Nomor 22 Tahun (2009) tentang Lalu Lintas dan Angkutan Jalan.

Undang-Undang Nomor 38 Tahun (2004) tentang jalan, pengelompokan jalan umum
Published
2021-11-27